Location: Chilas, District Diamir, Gilgit-Baltistan
Project Cost: PKR 80 billion
Diamir-Basha Confidence Building Measures is an Umbrella project consisting of Buildings, Roads, Hydropower, Water Supply, Project Colony and other infrastructure projects.
Location: F.R Bannu, KP
Weir/Dam Type: Earth Core Rockfill Dam (ECRD)
Commissioned: 1962
Dam Height: 30m
Raising Height: 7m
Reservoir Capacity: 100,000 acre-foot
Command Area: 170,000 Acres
Project Cost: PKR 5.156 billion
Location: Dargai, Malakand, KP
Weir/Dam Type: Diversion from Channel
Power Generation: 81 MW
Design Discharge: 51 m3/s
Net Head: 181 m
Length of Power Tunnel: 3.3 km
Annual Energy: 549 GWh
Project Cost: PKR 5.750 billion
Location: South Waziristan
Type: Roller Compacted Concrete (RCC) gravity
Dam Height: 133m
Power Generation Capacity: 17.4 MW
Command Area: 163,000 Acres
Length of Main Canal: 60 km
Gross storage capacity: 1.140 MAF
Main Canal: (Design Discharge): 24 cumecs
Project Cost: PKR 25.92 billion
Location: Malakand and Mardan Districts KP
Command Area: 25000 acres
Discharge: 200 Cusecs
Main Canal Length: 39 Km
Distributaries and Minors: 85 km
Project Cost: PKR 3.46 billion
Location: Khyber, Bajour and Mohmand Districts, KP
FWRDP was an Umbrella project consisting of 4 small Dams, 18 diversion Weirs, 3 CAD projects, 3 Solar Lift Irrigation Schemes, 5 Infiltration Galleries.
New Command Area: 10,670 acre
Command Area Development: 13,875 acres
Watershed Management: 12,479 acres
Project Cost: PKR 6.07 billion
Location: Gilgit
Design Discharge: 74 m3/s
Power: 40 MW
Net Head: 60.4 m
Diversion Weir (height): 19 m
Length of Weir: 198 m
Headrace Tunnel (dia): 6.3 m
Project Cost: 20.5
Location: Lasbela, Baluchistan
Height: 53.64 m
Catchment Area: 26,941 sq. km
Reservoir Area: 8,831 ha
Gross Storage Capacity: 1,487.58 Mm3
Design Capacity: 15,857 cumec
Feeder Canals Length: 85.91 km
Distributaries (19 nos.): 110.59 km
Location: Chitral, KP
Weir/Dam Type: Run of the river
Power Generation: 108 MW
Design Discharge: 30 cumec
Gross Head: 436 m
Headrace Tunnel: 3.8 km
Annual Energy: 442 GWh
Project Cost: PKR 29.77 billion
Location: Balakot – Mansehra, KP
Weir/Dam Type: Run-of-the-River
Power Generation: 300 MW
Design Discharge: 154 cumec
Gross Head: 229 m
Tunnel: 9.1 km
Annual Energy: 1143 GWh
Project Cost: PKR 94.5 billion
Location: Jabori Village, Mansehra – KP
Weir/Dam Type: Run-of-the-River
Power Generation: 10.2 MW
Design Discharge: 8 cumec
Gross Head: 148 m
Tunnel: 2.8 km
Annual Energy: 71.1 GWh
Project Cost: PKR 27.86 billion
Location: Karora, Shangla – KP
Weir/Dam Type: Run-of-the-River
Power Generation: 11.8 MW
Design Discharge: 9.75 cumec
Gross Head: 142 m
Tunnel: 2.94 km
Annual Energy: 71.39 GWh
Project Cost: PKR 37.8 billion
Location: Matiltan, Swat, KP
Weir/Dam Type: Run-of-the-River
Power Generation: 84 MW
Design Discharge: 42 cumec
Gross Head: 253 m
Tunnel: 6.67 km
Annual Energy: 346 GWh
Project Cost: PKR 16 billion
Location: Khyber District
Weir/Dam Type: Earth Core Rockfill Dam (ECRD)
Spillway Design: 110,000 cusecs
Dam Height: 70m
Raising Height: 7m
Reservoir Capacity: 37,000 acre-foot
Treatment Plant: Slow Sand filter plant
Project Cost: PKR 9.96 billion
Location: Thakot, Kohistan, KP
Weir/Dam Type: RCC
Power Generation: 4814 MW
Design Discharge: 3400 cumec
Gross Head: 159 m
Tunnel: 28 km
Annual Energy: 22180 GWh
Project Cost: USD 7698.34 million
A Data collection/Survey on livelihood improvement through vocational training for Afghan refugees and host communities.
Social Survey for Pilot Studies: Sept 2022-July 2024